| Pilot Implementation | ||
| OEE Awareness | ||
| Implementation step | Output | Duration |
| Management session | Complete image of OEE. The role of management, middle management and operators in implementation, daily OEE measurement and improvement is clear. | 1 day |
| Definition session | OEE definitions are produced by a multifunctional production team. | 1 day |
| Operator training | Operators understand the OEE concept and the role they play in it. | 1 day |
| Analysis workshop | After 4-6 weeks the OEE details are evaluated on-site. | 1 day |
| Software Implementation | ||
| Implementation step | Output | Duration |
| Install | OEE Toolkit is installed. | 20 Min |
| Configure | Definitions from definition session are included in OEE Toolkit. | During definition session |
| User training | Users can work with OEE Toolkit. | 1 hour |